South Metro Fire Station 23, Aurora
A shower room remodel inside a working fire station, taken from demolition to final inspection in under three months.
Underground
CompleteInspection passed August 27, 2026The crew isolated the bathrooms, removed the old fixtures and rebuilt the plumbing in the crawl space below the shower rooms. The station's utility sink and washer were reconnected early so the firefighters could keep using them.
Work completed
- Toilets, sinks and shower trim removed
- Ball valves installed to isolate the bathrooms
- Utility sink and washer reconnected to water
- New plumbing installed in the crawl space
- Inspection passed
Rough-in
CompleteInspection passed September 21, 2026New water lines, drains and vents went into the walls while the electrical crew worked the same rooms. The building had no hot water recirculation line, so one was added and tied into the existing system.
Work completed
- PEX water lines run to every bathroom
- Drain, waste and vent piping installed
- Floor drains set
- Condensate line rerouted into the wall
- Hot water recirculation line added
- Hot and recirculation lines insulated
- Rough-in inspection passed
Trim
CompleteCompleted October 14, 2026Final
CompleteFinal inspection completed November 3, 2026Planning a commercial build or remodel?